Ⅰ.The project is an iron concentrator with a daily processing capacity of 10,000t. Our Company is responsible for process design, civil engineering design and guidance, equipment manufacturing, non-standard parts design, water circuits, electric circuits, plants, and installation.
Ⅱ.The project is an iron concentrator with a daily processing capacity of 10,000t. Our Company is responsible for process design, civil engineering design and guidance, equipment manufacturing, non-standard parts design, water circuits, electric circuits, plants, and installation. Mechanical dewatering is adopted for both concentrate and tailings of the project, thus achieving zero discharge and recovery of recycle water and meeting the national green mine requirements. The tailings flow into the tailings pond for natural dewatering.